French nuclear group Framatome said it is close to finalizing an investment of more than 1 billion euros to build what it calls the world's largest forge in Le Creusot, in the Saone-et-Loire region of France. The plant, named Forge+, is designed to bring home the production of parts for France's future second-generation nuclear reactors.
Forge+ will sit on a 10.5-hectare site next to Framatome's existing facilities in Le Creusot. The factory itself will cover 40,000 square meters, roughly the size of five football pitches, according to a public consultation document on the project.
The plant is expected to open in 2030 and create 200 direct jobs, the same document states. It will house furnaces capable of heating 450 tonnes of steel to 1,300 degrees Celsius, along with a giant press able to shape enormous metal components.
A question of sovereignty
Gregoire Ponchon, chief executive of Framatome, told the news agency Bloomberg that the project is driven by a goal of industrial sovereignty. Currently, the only forges capable of producing the largest reactor parts, such as vessel heads, are located in Asia, in Japan, South Korea and China.
With renewed global interest in nuclear power, those manufacturers could end up prioritizing their own domestic markets, which risks delaying construction timelines for French power plants. France's EPR2 program calls for building six new-generation reactors across three existing nuclear sites: Penly, Gravelines and Bugey.
New workshop inaugurated
It is with this goal in mind that French Industry Minister Sebastien Martin inaugurated a new Framatome workshop in Le Creusot this week. The workshop specializes in manufacturing internal reactor vessel components, parts that are currently imported from the Czech Republic.
Bernard Fontana, chief executive of EDF, told the local outlet Creusot Infos that the inability to produce these components on French soil amounts to a genuine technological dependency.
Submarines and a future aircraft carrier
Fontana also said the new workshop is meant to respond to the growing global trend of extending the operating lifespans of nuclear power plants. He added that the facility will supply parts for the French Navy's nuclear submarines and for its next aircraft carrier.
According to Framatome, the future Forge+ factory will double the company's capacity to produce forged parts, with estimated output of 200 parts per year, enough to equip two new reactors annually.
What happens next
The Forge+ plant is expected to be operational in 2030, with annual output enough to equip two new nuclear reactors.
Test yourself
Where is Framatome building the world's largest forge?
What is the estimated investment for the Forge+ project?
Which countries currently hold the only forges able to make the largest reactor parts?